Cogeneration Plant for Paper Machine
Design and construction of a cogeneration plant to support paper machine operations, including installation of a circulating fluidized bed (CFB) boiler and back pressure steam turbine for energy efficiency and power generation.
Technical Specifications
- Boiler Type: Circulating Fluidized Bed (CFB) Boiler
- Boiler Capacity: 75 Ton/hr
- Operating Pressure: 100 BarG
- Steam Temperature: 550°C
- Turbine Type: Back Pressure Steam Turbine
- Power Output: 9.9 MWe
Scope of Work (SOW)
- Engineering and construction for electrical and control systems
- Installation of Master Control Panel (MCP) for Turbine Control
- Installation of Electrical Power Cables for Condensate Starter System
Project Value
9.72 Million THB
Project Timeline
Contract Period: 10 January – 23 March 2023