Cogeneration Plant for Paper Machine

Cogeneration Plant for Paper Machine

Design and construction of a cogeneration plant to support paper machine operations, including installation of a circulating fluidized bed (CFB) boiler and back pressure steam turbine for energy efficiency and power generation.

Technical Specifications

  • Boiler Type: Circulating Fluidized Bed (CFB) Boiler
  • Boiler Capacity: 75 Ton/hr
  • Operating Pressure: 100 BarG
  • Steam Temperature: 550°C
  • Turbine Type: Back Pressure Steam Turbine
  • Power Output: 9.9 MWe

Scope of Work (SOW)

  • Engineering and construction for electrical and control systems
  • Installation of Master Control Panel (MCP) for Turbine Control
  • Installation of Electrical Power Cables for Condensate Starter System

Project Value

9.72 Million THB


Project Timeline

Contract Period: 10 January – 23 March 2023